Legislation Details

File #: 21-6134   
Type: Board Letter for Action Status: Agenda Ready
File created: 8/11/2026 In control: Engineering, Operations, and Technology Committee
On agenda: 9/15/2026 Final action:
Title: Authorize (1) an increase of $172,849,771 to an existing design-build agreement with J.F. Shea Construction Inc. for a new not-to-exceed amount of $276,209,771 to authorize Phase 2B of the Sepulveda Pump Stations project; (2) an increase of $1.59 million to an existing agreement with Carollo Engineers Inc. for a new not-to-exceed amount of $4.89 million to serve as the owner’s advisor; and (3) an increase of $857,000 to an existing agreement with Parametrix Inc. for a new not-to-exceed amount of $1.402 million for cost estimating and scheduling services; the General Manager has determined that the proposed action is exempt or otherwise not subject to CEQA
Sponsors: EOT