Legislation Details

File #: 21-2546   
Type: Board Letter for Action Status: Passed
File created: 7/17/2023 In control: Engineering, Operations, and Technology Committee
On agenda: 8/15/2023 Final action: 8/15/2023
Title: Award an $1,962,691 contract to Structural Preservation Systems for urgent relining of three pipe segments on the Sepulveda Feeder; and authorize an increase of: (1) $280,000 to an agreement with HDR Engineering Inc., for a new not-to-exceed amount of $15,780,000; and (2) $240,000 to a land lease agreement with Los Angeles Community College District for a new not-to-exceed amount of $1,090,000; the General Manager has determined that the proposed actions are exempt or otherwise not subject to CEQA
Sponsors: EOT
Attachments: 1. 08152023 EOT 7-1 B-L, 2. 08152023 EOT 7-1 Presentation