Legislation Details

File #: 21-3616   
Type: Board Letter for Action Status: Passed
File created: 7/3/2024 In control: Engineering, Operations, and Technology Committee
On agenda: 8/20/2024 Final action: 8/20/2024
Title: Authorize an increase of $840,000 in change order authority to an existing contract with Steve P. Rados for the installation of an isolation valve for the Wadsworth Pump Plant Bypass Pipeline; the General Manager has determined that the proposed action is exempt or otherwise not subject to CEQA (This action is part of a series of projects that are being undertaken to improve the supply reliability for State Water Project dependent member agencies)
Sponsors: EOT
Attachments: 1. 08202024 EOT 7-3 B-L, 2. 08192024 EOT 7-3 Presentation