Title:
|
Authorize an increase of $840,000 in change order authority to an existing contract with Steve P. Rados for the installation of an isolation valve for the Wadsworth Pump Plant Bypass Pipeline; the General Manager has determined that the proposed action is exempt or otherwise not subject to CEQA (This action is part of a series of projects that are being undertaken to improve the supply reliability for State Water Project dependent member agencies)
|