Title: Award an $18,840,000 contract to Steve P. Rados Inc. to construct a surge protection facility on the Inland Feeder as part of the water supply reliability improvements in the Rialto Pipeline service area; the General Manager has determined that the proposed action is exempt or otherwise not subject to CEQA (This action is part of a series of projects that are being undertaken to improve the supply reliability for State Water Project dependent member agencies.)
Sponsors: EOT
Attachments: 1. 11142023 EOT 8-1 B-L, 2. 11142023 EOT 8-1 Presentation