Legislation Details

File #: 21-1964   
Type: Board Letter for Action Status: Passed
File created: 2/18/2023 In control: Engineering, Operations, and Technology Committee
On agenda: 3/14/2023 Final action: 3/14/2023
Title: Authorize agreement with Black & Veatch Corporation, Inc. in an amount not to exceed $8 million for the preliminary design of conveyance Reach 1 of the Pure Water Southern California program; authorize agreement with HDR Engineering, Inc. in an amount not to exceed $9 million for preliminary design of conveyance Reach 2 of the Pure Water Southern California program; and adopt a resolution to support a grant application to the U.S. Bureau of Reclamation for water recycling and desalination planning and authorize the General Manager to accept the grant if awarded; the General Manager has determined that the proposed actions are exempt or otherwise not subject to CEQA
Sponsors: EOT
Attachments: 1. 03142023 EOT 7-3 B-L, 2. 03132023 EOT 7-3 Presentation, 3. 9338 Resolution