Legislation Details

File #: 21-2056   
Type: Board Letter for Action Status: Passed
File created: 3/19/2023 In control: Engineering, Operations, and Technology Committee
On agenda: 4/11/2023 Final action: 4/11/2023
Title: Authorize an agreement with Stantec Consulting Services, Inc. in an amount not to exceed $900,000 for a detailed seismic analysis of the Lake Skinner outlet tower; and award a $1,174,475 procurement contract to B&K Valves and Equipment, Inc. for the replacement of two valves at the Lake Skinner outlet tower; the General Manager has determined that the proposed action is exempt or otherwise not subject to CEQA
Sponsors: EOT
Attachments: 1. 04112023 EOT 7-3 B-L, 2. 04102023 EOT 7-3 Presentation