Legislation Details

File #: 21-3615   
Type: Board Letter for Action Status: Passed
File created: 7/3/2024 In control: Engineering, Operations, and Technology Committee
On agenda: 8/20/2024 Final action: 8/20/2024
Title: Authorize an agreement to Carollo Engineers Inc. in an amount not to exceed $1.3 million for owner’s advisor services to assist with progressive design-build project delivery on the Lake Mathews Pressure Control Structure and Electrical System Upgrades; the General Manager has determined that the proposed action is exempt or otherwise not subject to CEQA
Sponsors: EOT
Attachments: 1. 08202024 EOT 7-2 B-L, 2. 08192024 EOT 7-2 Presentation